Which item is NOT required on a commercial building permit application?

  1. Signature of the building owner or agent

  2. Description of the land for proposed work

  3. Proposed building occupancy use group

  4. Projected date for beginning construction

The correct answer is: Projected date for beginning construction

The projected date for beginning construction is not typically a required part of a commercial building permit application. Permitting authorities focus on essential information that demonstrates compliance with safety, zoning, and construction standards, rather than specific timelines for project commencement. The signature of the building owner or agent is necessary because it signifies approval and consent to pursue the proposed work. A description of the land for the proposed work is also vital, as it helps the permitting authority assess zoning compliance and any environmental factors. Furthermore, understanding the proposed building occupancy use group is crucial for determining the building's compliance with applicable codes and regulations, as different use groups may have varying requirements for safety, accessibility, and utility. In summary, while planning dates are important for project management, they are not a standard requirement for the actual permit application process, which focuses on legal and regulatory compliance rather than project scheduling.